4.
Set the full up travel first using the factory templates. Making sure both the control column and
the elevator trim is hard back. Adjust the female ball ends in or out if adjustment is needed.
5.
To establish the neutral position, align balance horn with horizontal stabiliser.
6.
Adjust cable rod ends to achieve UP and DOWN travel using the Elevator Rigging Template
(Templates can be supplied by Jabiru Aircraft Pty Ltd).
7.
DO NOT
move the Cable Anchors
– These are factory set.
8.
Ensure lock nut is tight on rod ends and that cable is visible through hole in spherical bearing.
Figure 127
– Elevator Travel Limits (all J-Series)