4. Reinstall the mounting brackets to the top and bottom of the back of the Power Center using the four
(4) screws that were removed in
Step 2
. Ensure that the brackets are rotated from the original shipping
position (see Figure 11).
Reinstall Mounting Brackets
(Ensure to Rotate from
Original Shipping Position)
Figure 11. Reinstall Mounting Brackets on Power Center
5. Hang the Power Center on the surface using the three (3) holes drilled in
Step 3
. With the Power Center
in place, mark three holes for the bottom bracket mounting.
NOTE
As with the top brackets, the bottom bracket requires three (3) mounting holes. The three mounting holes are
four inches (4") apart center to center.
6. Drill the holes and install the screws.
7. Level the Power Center and tighten all screws, ensuring that the Power Center is securely fastened to
the mounting surface.
8. Check source voltage. (All units are factory wired for 230 VAC
).
In order to use on 115 VAC, the
internal factory wiring of the power center must be changed. (See wiring diagram page 7 Figure 2).
3.4 Earth Bonding (Grounding)
A solid, copper # 8 awg (8.4 mm
2
) wire is
recommended
for connecting the power center to a Permanent
Earth Ground connection that is acceptable to the local inspection authority. Refer to your local codes for
the acceptable grounding wire gauge. Attach the bonding point located on bottom of the power center to
a Common Earth Bonding Point. Do not use the PureLink Power Center as the Common Bonding Point.
Each piece of non-PureLink related pool equipment requiring a ground should be bonded to the Common,
Approved Earth Bonding Point.
Never ground pool pump to the power center
.