3.4 Remove Pump Lid
1. Make sure that the pump is turned off.
2. Make sure that the switch to the circuit breaker
that powers the pump motor is turned off.
wARNING
ELECTRICAL SHOCK HAZARD
Turn off the pump and the main breaker in the pump
electrical circuit before starting the procedure. Failure
to comply may cause a shock hazard, resulting in
severe personal injury or death.
wARNING
ELECTRICAL SHOCK HAZARD
Due to the potential risk of fire, electric shock, or
injuries to persons, Zodiac
®
Pumps must be installed
in accordance with the National Electrical Code
(NEC), all local electrical and safety codes, and
the occupational Safety and Health Act (OSHA).
Copies of the NEC may be ordered from the National
Protection Association, 470 Atlantic Ave., Boston,
MA 02210, or from your local government inspection
agency.
In Canada, Zodiac Pumps must be installed in
accordance with the Canadian Electrical Code
(CEC).
To install an AquaLink
®
RS controller (Rev O or
later) or an AquaLink PDA (Rev 4.0 or later):
1. Remove power from the VS-FHP pump by
disconnecting the high voltage lines or by opening
any breaker to which the VS-FHP pump power is
connected.
wARNING
ELECTRICAL SHOCK HAZARD
Turn off all switches and the main breaker in the
VS-FHP pump electrical circuit before starting the
procedure. Failure to comply may cause a shock
hazard, resulting in severe personal injury or death.
2
. Slide dip switches 1 and 2 down, so they are in the
OFF position. See Figure 5.
3. Select the desired address(es) for the
VS-FHP
pump
by setting dip switches 3 and/or 4, as shown
in
Section 3.3, VS-FHP Pump Dip Switch Settings.
4. Connect the other end of the cable to an RS-485
connector on the AquaLink RS (or multiplexer
interface board), matching wire colors with
connector positions
as follows: 1-red, 2-black,
3-yellow, and 4-green. See Figure 5.
5. Restore power to the VS-FHP pump and verify the
operation of the controller.
6. Refer to the appropriate manual to operate the
pump: AquaLink RS Owner’s Manual, 6593, or
AquaLink PDA Owner’s Manual, H0572300.
3.3 VS-FHP Pump Dip Switch Settings
As shown in
Figures 4 and 5,
the 4-position dip
switch is located at the rear of the VS-FHP pump. This
dip switch serves two (2) functions: it selects the pump
address, and it determines what type of controller will
be used with the pump.
The tables below show the dip
switch settings
.
Switch
1
Switch
2
Controller
OFF
OFF
AquaLink RS or AquaLink PDA
ON
OFF
AquaLink RS or AquaLink PDA
OFF
ON
AquaLink RS or AquaLink PDA
ON
ON
Variable Speed
Controller JEP-R
Switch 3 Switch 4 Pump Address
OFF
OFF
PUMP 1
ON
OFF
PUMP 2
OFF
ON
PUMP 3
ON
ON
PUMP 4
Variable-Speed
Pump
4 3 2 1
RED
BLACK
YELLOW
GREEN
RS485 Cable
BLACK YELLOW
RED
GREEN
Connect to
AquaLink RS
RS-485 Connector
(or Multiplexer
Interface Board)
S1
S2
RESET
SERVICE
TIME OUT
FIL
TER PUM
P
AUX
1
AUX
2
AUX
3
AUX
4
AUX
5
AUX
6
AUX
7
RS6 & RS8 ONLY
RS8 ONLY
HEATER
SOLAR
POOL MODE
SPA MODE
SPA DRAIN
SPA FILL
AUTO
6 5 4 3 2 1 10 9 8 7 6 5 4 3 2 1
4 3 2 1 4 3 2 1
AquaLink RS
RS-485 Connectors
4-Position
DIP Switch
Figure 5. wiring AquaLink RS Controller or
AquaLink PDA to VS-FHP Pump
Page 12
Jandy
®
FloPro™ Variable-Speed Pump Series VS-FHP
|
Installation and Operation Manual
ENGLISH