INSTALLATION INSTRUCTIONS (cont.)
CleanIng
1. Remove all loose debris. Construction plaster or excess
grout can be removed with the use of a wood (edge)
trowel.
2. Paint or tar stains may need to be removed with a
cleaner such as paint thinner, turpentine, or isopropyl
alcohol (rubbing alcohol). Never allow the cleaner to
soak against the acrylic surface for long periods of time.
Always rinse the surface immediately following the
use of cleaners.
3. Follow the manufacturer’s instructions for safe use of
cleaning products. If the surface becomes scratched or
dulled, it may be restored by using a quality plastic polish,
like Novus Plastic Polish No. 2 (available from the Jason
Dealer). It is always preferable to protect the acrylic
surface during installation to minimize cleanup and
prevent surface damage.
waTer TesTIng
Before finishing the installation, it is recommended that the
bath be water tested and the plumbing tested for leaks.
1. Before water testing the bath, make sure all plumbing
connections are tight. DO NOT OVERTIGHTEN.
2. Fill and operate the bath. Close the drain and fill the
bath with water to at least 10 inches [25 cm] below the
bath deck. The inlet temperature should not exceed 40°C
(104°F). Refer to the FILLING AND DRAINING section
of this owner’s manual for more information.
NEVER RUN THE PUMP WITHOUT ENOUGH
WATER IN THE BATH TO COVER THE JETS.
3. Inspect the plumbing for leaks.
4. Turn the equipment Off and then drain the water. The
bath unit and its plumbing are designed to drain after each
use whether used as a hydrotherapy bath, soaking bath,
or when taking a shower.