P/N 960-000186R_Rev. A {EDP #253995}
© 2016, JAPAN CASH MACHINE CO., LTD.
2 0
RDM-100™ Series Retail Deposit Module
Transport Assembly Top Cover Installation
When installing the Transport Assembly Top Cover, the shaft will slide into the cutout easily without
excessive force.
T
RANSPORT
A
SSEMBLY
C
LEANING
Open the Transport Assembly Cover and clean each Sensor and Roller on the Transport Path.
Figure 39
Cutout Location
Cutout
Be sure the Shaft is
installed into the
Cutouts on both sides
correctly.
If the Shaft is not
installed correctly, the
Unit could become
damaged.
Transport Assembly Sensor/Roller Locations
Figure 40
Transport Assembly Sensor/Roller Locations
BAU
Front
Positioning
BNF Stop
Sensor 2
Sensor
Pinch
Roller
Transport
Roller
Caution: When cleaning is performed by removing the Transport Assembly Top Cover, take care not to damage the
Unit. Refer to “BNF Stop Sensor 1, 2 Cleaning” on page 19.