P/N 960-000164R_Rev. 3 {EDP #213631}
© 2018, JAPAN CASH MACHINE CO., LTD.
2 - 2 3
Installation
iPRO-RC™ Series Banknote Recycler
Section 2
Operational Flowchart (Continued)
Figure 2-21 depicts a typical iPRO-RC™ Abnormal Error flow process.
Figure 2-21
Figure 2-21
iPRO-RC Operational Flowchart (Abnormal Error)
E) Return from the Figure 2-20 “Dispensing”
Flow on page2-22 of this Service Manual
b) Sending Abnormal Signal
d) Stop transportation
a) Was transportation retried two (2) times? (*6)
c) Is a Banknote being dispensed from the Recycler
Unit?
C3) Return to the Figure 2-23 “Retrieving/Cash Box”
Flow on page2-25 of this Guide
*6). The specific Banknote position, or an abnormal Banknote may be treated as an “Abnormal Error” occurrence condition.