Installation and Operating Instructions ECOVARIO®114 D
50
Subject to change without notice!
7.3
Work schedule commissioning
1. Check installation
Th e servo amplifi er is disconnected from the supply. Check the wiring for completeness, short circuits and
ground faults (according to connection diagram in Fig. 6.2.1).
2. Zero enable
Connect the ENABLE input of the respective axis to 0 V (connector X1A (axis 1) or X1B (axis 2)).
3. Switch on 24 V logic supply
Apply the 24 V control voltage at the connector X1A between the pins GND and +24 V; aft er an initializing
phase of about 3 s the LED display shows the operation mode of the servo amplifi er.
4. Rectify eventual errors
If the display shows an error, the error has to be rectifi ed before commissioning (cf. chapter 7.3.2).
5. Start setup soft ware
Connect a PC to the PC interface (X13) of the ECOVARIO® 114 D (or via CAN dongle to the interface X21)
and start the commissioning and operation program ECO Studio. Here, establish the logic connection bet-
ween PC and ECOVARIO® 114 D.
Note: For each axis a separate ECO Studio session has to be started.
6. Device confi guration and mechanical confi guration
Device confi guration and mechanical confi guration must be adjusted to each specifi c case.
Incorrect parameter settings can cause damage or destruction of machine parts.
With the help of the ECO Studio device confi guration wizard and of the mechanical confi guration wizard
carry out the basic settings for the operation of ECOVARIO®. A detailed description of soft ware commis-
sioning can be found in the „ECO Studio Operation Manual ECOVARIO®, ECOSTEP® and ECOMPACT®“
and in the ECO Studio help system.
Before switching on the power supply the following items 7 to 10 have to be observed.
7. Check safety equipment
Before switching on the voltage it is vital to check if all safety equipment that protects from
touching live parts and from the consequences of indeliberate movements functions proper-
ly.
8. Zero demand values
Before switching on the power supply the analog and digital demand values for position and speed should
be zeroed.
9. Switch on power supply
Th e power supply should only be switched on with the on/off switches of a contactor circuit.
10. ENABLE
0,5 s aft er switching on the power supply, the enable signal of the respective axis can be changed to „high“
(24 V level at input X1A: Enable1 or X1B: Enable2). If the motor vibrates or hums the value of the p-gain
should be reduced (ECO Studio: in the navigation area select the „Controller“ entry and then the „Velocity
Controller“ tab).