background image

 

 

43211B 

 

 
 
 
 
 
Optional: Vehicle Lockout Wiring for 1995-2014 DS Golf Cars 

 

 

8.  Start by 

locating “Wire 

a

ssemblies A & B”

. Using these 2 wire assemblies A & B make the following connections as 

shown in the picture below. 

 

 

9.  Now that you have wire assemblies A & B connected make the following connections indicated in the wire diagram 

above called BY-PASSED OBC.  

10.  Re-install previously removed hardware from step 6 (page 2) on battery Negative ("-") post. Refer to your particular 

battery manufacture for torque specifications on battery hardware. 

11.  Switch the Run/Tow switch to the RUN position. 

12.  Re-install seat. 

Installation complete. 

Summary of Contents for 43212S

Page 1: ...connect the single Packard connection which connects the vehicles charging receptacle to the OBC 7 Using the supplied Y wire assembly in the kit connect it between the previously disconnected Packard connector making sure the connections are fully engaged and route the ring terminal end of the wire assembly out from this area to the battery storage compartment 8 Optional Vehicle Lockout Inhibit ci...

Page 2: ...tud 5 Re install previously removed hardware and torque to 22 in lbs 6 Remove hardware from the Negative post of the last battery in series on your pack 7 Place the large 5 16 ring terminal of the single wire on the battery Negative post 8 Optional Vehicle Lockout Inhibit circuit See page 4 at this time if you would like to activate this feature 9 Re install previously removed hardware from step 6...

Page 3: ...ly removed covers from steps 5 and then 4 page 1 10 Connect 5 16 ring terminal from y wire routed in step 7 along with ALL wires previously removed in step 3 to the Negative post on the last battery in the series or pack and re install hardware from step 3 Refer to your particular battery manufacture for torque specifications on battery hardware 11 Switch the Run Tow switch to the RUN position 12 ...

Page 4: ...9 Now that you have wire assemblies A B connected make the following connections indicated in the wire diagram above called BY PASSED OBC 10 Re install previously removed hardware from step 6 page 2 on battery Negative post Refer to your particular battery manufacture for torque specifications on battery hardware 11 Switch the Run Tow switch to the RUN position 12 Re install seat Installation comp...

Reviews: