9
Referring back to Figure 10:
4. Insert one end of
chain link
(D) into
chain
anchor
(C).
5. Insert
pin stopper
(B) through
chain anchor
(C)
and
chain link
(D) and secure with
split pin
(A).
Continue with
section 8.4
, proceeding to the
section that applies to your hoist.
7.4
Completing load chain installation
The following procedure assumes that the
load
chain
has been attached to the
chain anchor
and
fed through the
load chain sprocket
as described in
the previous section. This procedure will complete
the load chain and bottom hook installation.
7.5
Chain installation: 0.5T thru 2T
Referring to Figure 12:
1. Remove
lock nut
and bolt (D)
from lower hook.
2. Insert the last
chain link
(C) into lower hook
slot.
3. Re-insert bolt through lower hook slot and
chain link.
4. Install lock nut onto bolt and tighten.
7.6
Chain installation: 3T and 5T
Referring to Figure 13:
1. After installing the load chain into
load chain
sprocket
(B), run the remaining chain through
your hand to remove any twist. The last link of
the chain must be in the same direction as the
first. If not, cut off the last link.
2. Insert the last link into pulley of
lower hook
(C).
3. Pull
load chain
through and up from underside
of pulley (C,D).
4. Remove
lock nut
and
chain anchor pin
in
upper hook slot
(E).
5. Insert the last link into upper hook slot.
6. Check that load chain is not twisted.
7. Reinstall chain anchor pin through upper hook
slot and last chain link, and secure with the
lock nut.
Figure 12
(1/2 through 2-ton hoists)
Figure 13
(3-ton and 5-ton hoists)