Wrap entire firebox and gather
in 100mm R3.5 fibreglass
insulation.

100mm clearance from
outer flue to header.

Header stud to be on
edge to ensure adequate
clearance

4. Clearance requirements

Fig 3.5

The Jetmaster 1500 and 1200 Open Fronted Fireplace and 75mm Hebel PowerPanel enclosure are to be installed with a 455mm
double skin flue kit (1500 single spigot gather) and 405mm double skin flue kit (1200 single spigot gather).

Double spigot gathers require twice the quantity of twin skin pipe (

refer to page 11 for flue requirements

)

The appliance and Flue Combination should be installed at the following clearances:

• Combustible mantle shelf clearances should be 1000mm above the opening as per clause 3.4.1.3(b) of AS/NZS 2918:2018

• Non-combustible materials - 500mm above opening

• The rear, sides and front of enclosure must consist of 75mm Hebel PowerPanel.

• The Hebel PowerPanel sides of the enclosure must be installed 15mm from the appliance with 100mm R3.5 insulation

compressed to 15mm between the PowerPanel and the appliance.

• The Hebel PowerPanel rear wall must be installed a minimum of 135mm from the rear of the appliance below the appliance

gather and 15mm at the top of the appliance gather with 100mm R3.5 insulation compressed to 15mm between the
appliance and Hebel PowerPanel.

• Double spigot gather is narrower. It is important to ensure Hebel cavity is within 15-25mm of the gather and the specified

insulation is compressed to this amount.

• The appliance rear wall, the gather, sides and all other external parts of the appliance must be wrapped in 100mm R3.5

insulation between the PowerPanel enclosure up to the height of the flue outer casing. Fig 3.5

• The Flue penetration through the ceiling must have a 50mm gap in all directions around the outer casing of the flue from

combustible materials.

• The front wall of the enclosure clearance box enclosure must be made of Hebel PowerPanel to a height of 1600mm above the

hearth and must extend to 75mm either side of the appliance.

• The External rear wall of the PowerPanel Enclosure can be placed against a combustible wall.

• The External side walls of the PowerPanel Enclosure can be placed against a combustible wall.

Clearance to an adjacent wall for units 1500
& 1200 and should be 1200mm as per clause
3.2.2(b) AS/NZS 2918:2018.

Double spigot installations must maintain the same clearance
specifications.
Ensure to fill insulation between the two sets of outer flue casings up
to 200mm above the gather.

Double spigot termination heights should be offset by 500mm to
reduce downdraft effects.

Summary of Contents for 1200 series

Page 1: ...only Other fuels may over fire and generate poisonous gases i e carbon monoxide Do not store or use gasoline or other flammable vapors and liquids in the vicinity of this or any other appliance Do not...

Page 2: ...11 6 General use Attaching firescreen lighting a fire 12 6 General use Fuels Cleaning Maintenance Safety 12 AS NZS 2918 2018 General notes Thank you for purchasing a Jetmaster fireplace Please read th...

Page 3: ...is with height of chimney minimum 4 6 metres as per AS NZS 2918 2018 C Negative Pressure Negative pressure results from the imbalance of air available for the appliance to operate properly It can be...

Page 4: ...flow of outdoor air for all combustion appliances and exhaust equipment Ensure cental heating and air conditioning return vents are not located in the vicinity of the appliance Avoid installing the a...

Page 5: ...1500 dual spigot gather 1550 1600 600 1000 400 300 350 450 150 Measurements are in mm and provided as a reference only Double flue size is 50mm bigger than the above F measurements Dual spigot will r...

Page 6: ...plications an AGA approved cowl must be used C D Measurements are in mm and provided as a reference only Due to the nature of thick welded steel it is normal and expected for some imperfections and sl...

Page 7: ...GOT 1600 1730 750 1500 DOUBLE SPIGOT 1600 1730 690 Note Timber framing should be constructed using normal framing methods Image above is an example only Do not install finishing materials around the c...

Page 8: ...ce see joint AS NZS 2918 2018 3 3 2 The floor protector should extend 900mm in front of the appliance opening and be placed centrally in the 1650mm width 100mm thick floor protector projection can con...

Page 9: ...op of the appliance gather with 100mm R3 5 insulation compressed to 15mm between the appliance and Hebel PowerPanel Double spigot gather is narrower It is important to ensure Hebel cavity is within 15...

Page 10: ...ation cap away from trees adjacent structures uneven roof lines and other obstructions Your local dealer is the expert in your geographic area and can usually make suggestions or discover solutions th...

Page 11: ...crimp facing up to ensure water penetration on flue above roof runs out Rivet active flues together at crimped joins Fix outer non active flues to active inner flues use 3 x 25mm self tapping screws...

Page 12: ...side towards you with the steel handle provided 2 In firebox lay your fire lighters 10 to 15 centimetres apart depending on the size of your firebox Do not use newspaper as a fire lighter On units th...

Page 13: ...S NZS 2918 General notes Fuels The quality of firewood is extremely important How long a tree has been felled or dead for does not indicate how dry the wood is The best way to dry wood is to split it...

Reviews: