background image

9. Gas Cylinder, Pipe Runs and
Sizes

(This work must only be carried out by a
person who is a registered LPGAS Association
installer.)

1 Jetmaster LP Gas Convectors must

be operated off one or more 48 kg
cylinders, depending on size of unit.
The cylinder(s) must be positioned
outside, as close as possible to the
appliance, and in any case not further
than 30 metres, the cylinders must be
away from heat sources, electrical
devices, drains, windows and
combustible materials, in accordance
with SABS 087 Part 1: March 1999.
Cylinders must always stand in the
VERTICAL position and must be fixed
so they cannot fall or be knocked
over. For best performance, avoid cold
areas and shade. Where the regulator
or pipework is in a position which is
liable to be very cold in winter, it is
advisable to lag them to prevent
freezing up. It is always advisable to
fix the regulator vertically rather than
horizontally. This will prevent any
condensation settling in the bottom
of the regulator which will freeze up
in the cold weather causing the Gas
Convector to shut down.

2 Check the Jetmaster Pipe Sizing Chart

below to choose the correct size of
pipe for the Gas Convector size and
length of run. Although Jetmaster
supplies 4 metres of 8 mm copper
tube with LP Gas Convectors, it is
not necessarily of sufficient size if
larger fire or longer than 4 metre run
are to be fitted. Be sure to fit the right
size pipe. Do not run more than one
gas fire off each supply, without first
checking the fitter’s supply chart. Any
queries please contact Jetmaster
Technical Department.

LP pipe size: From cylinder and
low pressure regulator (28
M b a r )   t o   g a s   a p p l i a n c e :

Copper tubing

8mm

15mm

LP Gas 

up to 

to 30 m

Convector

4 m

It is recommended by the LPGAS
Association that any pipe run greater
than 9 metres is supplied under high
pressure and a low pressure regulator
is fitted within 4 metres of the fire.

3 Having positioned the 48 kg gas

cylinder in a fixed position, connect
the regulator supplied to the flexible
hose, and the male hose connector
to the end of the copper tubing using
the compression fitting. These fittings
are supplied and should be used. If a
larger pipe is to be used then the
correct size of fittings will have to
be obtained.

4 Tighten the hose clamps and connect

the regulator to the cylinder. The
regulator should be protected from
rain and fixed in the vertical position
if possible alternatively angle the
regulator so that liquids cannot collect
on the top causing rusting of internal
components and subsequent
malfunctioning, i.e. the plastic cap
should not face upwards. The air vent
in the regulator must be pointing
downwards.

5 Cover the end of the gas pipe to

prevent dirt getting into it and
damaging the valve, which will
invalidate the Warranty.

INSTALLATION & OPERATING INSTRUCTIONS

7

INSTALLATION AND OPERATING INSTRUCTIONS:

550, 700 & 850 DE LUXE

550, 700 & 850 GAS CONVECTOR
INSTALLATION & OPERATING INSTRUCTIONS

Summary of Contents for 550

Page 1: ...INSTALLATION OPERATING INSTRUCTIONS 550 700 850DeLuxe GasConvector...

Page 2: ...from Instructions 4 5 Ventilation 5 6 Chimney 5 7 Preparatory Building Work 6 8 Fitting the Jetmaster Convector Box 6 9 Gas Cylinders Pipe Runs and Sizes 7 10 Fitting the Gas Burner 8 11 Positioning...

Page 3: ...Manual ControlValve fitted to 850 burner Pressure Test Point 5 16 8mm diameter nipple located on the inlet gas supply on the 550 and 700 burner Test point on the Baby Sit Manual ControlValve on the 8...

Page 4: ...m radius of the fire INSTALLATION OPERATING INSTRUCTIONS 3 INSTALLATION AND OPERATING INSTRUCTIONS 550 700 850 DE LUXE 550 700 850 GAS CONVECTOR INSTALLATION OPERATING INSTRUCTIONS In some countries a...

Page 5: ...e installation of this gas fireplace and the relevant clauses must be applied SABS 1539 2001 Appliances operating on LP Gas portable and mobile appliances safety aspects SABS 087 Part 1 March 1999 Con...

Page 6: ...ors one at ceiling height and one at floor level Most properties have a ventilator at ceiling height The lower vent can be made quickly and cleanly using a core drill and fitting a sleeve and grids at...

Page 7: ...ng fireplace opening mark and drill two securing holes in the base of the convector box and the hearth below and secure the convector box to prevent it from moving forward 7 Preparatory Building Work...

Page 8: ...tted Be sure to fit the right size pipe Do not run more than one gas fire off each supply without first checking the fitter s supply chart Any queries please contact Jetmaster Technical Department LP...

Page 9: ...12 mm drill for the gas pipe entry point Sleeve the gas pipe with metal plastic tubing where it is to pass through the wall of the convector box to protect it If the pipe run from the gas cylinder has...

Page 10: ...the correct position Adjustment on the support legs on the burner may be required 6 Open the gas supply and test for leaks as far as the valve attaching a manometer or U gauge to the test nipple makin...

Page 11: ...550 700 850 GAS CONVECTOR INSTALLATION OPERATING INSTRUCTIONS INSTALLATION OPERATING INSTRUCTIONS 10 INSTALLATION AND OPERATING INSTRUCTIONS 550 700 850 DE LUXE Front Options...

Page 12: ...e has a cut on its rear edge to clear the pilot hole Ensure that the pilot hole and flame strip are not obstructed 2 Position the back board centrally into the burner tray ensuring it is correctly sea...

Page 13: ...es and the back board 6 Position a third and final row of coals 5 on the 550GC 6 on the 700GC and 8 on the 850GC These should rest between the second row of coals and the top of the back board Leave a...

Page 14: ...are fitted properly The 2 pieces of ceramic that go onto the front ceramic support tray should be behind the stop lugs not on top or pushed down onto the lugs If these ceramics do not fit then a fine...

Page 15: ...e generator e g smoke match Once the fire is installed and opperational the installer must check for spillage Carry out the lighting procedure and turn the fire to high Allow to warm up for 5 minutes...

Page 16: ...ensing device fitted to this fire is also an atmospheric sensing device which shuts off both the main burner and pilot if evacuation of the combustion products is interrupted If the fire shuts itself...

Page 17: ...flame will have heated the flame supervision thermocouple sufficiently to operate a hold on magnet within the valve The knob should then be turned so that the pointer is approximately horizontal This...

Page 18: ...e operation 5 Once the pilot is lit continue and hold in the gas control knob for a further 10 15 seconds to establish the pilot If the pilot fails to remain alight repeat the procedure but hold the g...

Page 19: ...that cleaning replacement can be a dirty and dusty operation Suitable precautions should be taken Due to the intense temperatures reached in the fire some surface cracks may appear on the ceramic comp...

Page 20: ...y hand and remove any soot deposits by hand with a soft brush i e paint brush NOTE Due to the intense temperatures reached in the fire some surface cracks may appear on the ceramic components This is...

Page 21: ...lves cleaning and relaying the coals checking the pilot light and all joints checking ventilators and fume clearance and repainting the exposed parts It should take an hour to an hour and a half We ar...

Page 22: ...by main or by fax within 30 days of purchase 3 3 The Gas Grate Gas Convector burner and or firebox was installed by a registered LPGAS Association fitter and was purchased from an appointed Jetmaster...

Page 23: ...anga 10 Milli Street Middelburg Mpumalanga Tel 013 246 2600 Fax 013 246 2951 Richards Bay 63 Kabel Kring Road Alton Richardsbay Tel 035 797 5800 Fax 035 797 5818 Durban Cnr Meridian Solstice roads Umh...

Reviews: