SECTION 5 - BASIC HYDRAULIC INFORMATION & HYDRAULIC SCHEMATICS
3121619
5-61
9.
Loosen and remove bolts from tapered bushing and pis-
ton.
10.
Insert bolts in threaded holes in outer piece of tapered
bushing. Progressively tighten bolts until bushing is
loose. Remove tapered bushing from piston.
11.
By hand, screw the piston counterclockwise and remove
it from cylinder rod.
REMOVE SEALS USING A BRASS OR PLASTIC PICK ONLY. DO NOT USE A KNIFE,
SHARP OBJECT, OR SCREW DRIVER. MAKE NOTE OF SEAL ORIENTATION
BEFORE REMOVING FOR PROPER INSTALLATION.
12.
Remove and discard backup ring, o-ring, and backup
ring from inside grooves of piston. Remove and discard
two lock rings and seals from outer grooves of piston.
13.
Remove piston spacer from rod.
14.
Remove rod from holding fixture. Remove cylinder head
and washer ring.
15.
Remove and discard two wear rings, wiper seal, and rod
seal from inside of cylinder head. Remove and discard O-
ring and backup ring from outer groves of cylinder head.
CLEANING AND INSPECTION
1.
Clean parts thoroughly with approved cleaning solvent.
2.
Inspect cylinder rod for scoring, tapering, ovality, or
other damage. If necessary, dress rod with Scotch Brite
or equivalent. Replace rod if necessary.
3.
Inspect threaded portion of rod for excessive damage.
Dress threads as necessary.
4.
Inspect inner surface of cylinder barrel tube for scoring
or other damage. Check inside diameter for tapering or
ovality. Replace if necessary.
5.
Inspect threaded portion of barrel for damage. Dress
threads as necessary.
6.
Inspect piston surface for damage, scoring, or distortion.
Dress piston surface or replace piston as necessary.
7.
Inspect threaded portion of piston for damage. Dress
threads as necessary.
8.
Inspect seal and O-ring grooves in piston for burrs and
sharp edges. Dress surfaces as necessary.
9.
Inspect cylinder head inside diameter for scoring or
other damage, and for ovality and tapering. Replace as
necessary.
10.
Inspect threaded portion of head for damage. Dress
threads as necessary.
11.
Inspect seal and O-ring grooves in head for burrs and
sharp edges. Dress applicable surfaces as necessary.
12.
Inspect cylinder head outside diameter for scoring,
damage, ovality, and tapering. Replace as necessary.
13.
Inspect rod and barrel bearings for signs of correct
excessive wear or damage. Replace as necessary.
a.
Thoroughly clean hole, (steel bushing) of burrs, dirt
etc. to facilitate bearing installation.
b.
Inspect steel bushing for wear or other damage. If
steel bushing is worn or damaged, rod/barrel must
be replaced.
c.
Lubricate inside of the steel bushing with WD40
prior to bearing installation.
NOTE:
Lubrication is not required with nickel plated pins and
bearings. Install pin in composite bushing dry.
Figure 5-28. Tapered Bushing Removal
Summary of Contents for 1850SJ
Page 1: ...Service and Maintenance Manual Model 1850SJ 3121619 June 29 2018 Rev J AS NZS...
Page 2: ......
Page 21: ...3121619 xvii LIST OF FIGURES FIGURE NO TITLE PAGE NO Thispageleftblankintentionally...
Page 24: ...xx 3121619 LIST OF TABLES TABLE NO TITLE PAGE NO Thispageleftblankintentionally...
Page 50: ...SECTION 2 GENERAL 2 12 3121619 NOTES...
Page 55: ...SECTION 3 CHASSIS TURNTABLE 3121619 3 5 This page left blank intentionally...
Page 56: ...SECTION 3 CHASSIS TURNTABLE 3 6 3121619 Figure 3 4 Axle Hose Routing Sheet 1 of 2...
Page 57: ...SECTION 3 CHASSIS TURNTABLE 3121619 3 7 Figure 3 5 Axle Hose Routing Sheet 2 of 2...
Page 58: ...SECTION 3 CHASSIS TURNTABLE 3 8 3121619 Figure 3 6 Steering Axle Hydraulic Circuit...
Page 61: ...SECTION 3 CHASSIS TURNTABLE 3121619 3 11 Figure 3 9 Turntable Hydraulic System...
Page 92: ...SECTION 3 CHASSIS TURNTABLE 3 42 3121619 Figure 3 39 Swing Bearing Wear Tolerance...
Page 94: ...SECTION 3 CHASSIS TURNTABLE 3 44 3121619 Figure 3 41 Swing Bearing Removal Sheet 2 of 4...
Page 110: ...SECTION 3 CHASSIS TURNTABLE 3 60 3121619 Figure 3 54 Engine Electrical Circuit...
Page 169: ...SECTION 4 BOOM PLATFORM 3121619 4 7 Figure 4 1 Boom Hydraulic System...
Page 173: ...SECTION 4 BOOM PLATFORM 3121619 4 11 Figure 4 2 Boom Assembly Sheet 1 of 9...
Page 174: ...SECTION 4 BOOM PLATFORM 4 12 3121619 Figure 4 3 Boom Assembly Sheet 2 of 9...
Page 175: ...SECTION 4 BOOM PLATFORM 3121619 4 13 Figure 4 4 Boom Assembly Sheet 3 of 9...
Page 176: ...SECTION 4 BOOM PLATFORM 4 14 3121619 Figure 4 5 Boom Assembly Sheet 4 of 9...
Page 177: ...SECTION 4 BOOM PLATFORM 3121619 4 15 Figure 4 6 Boom Assembly Sheet 5 of 9...
Page 178: ...SECTION 4 BOOM PLATFORM 4 16 3121619 Figure 4 7 Boom Assembly Sheet 6 of 9...
Page 179: ...SECTION 4 BOOM PLATFORM 3121619 4 17 Figure 4 8 Boom Assembly Sheet 7 of 9...
Page 180: ...SECTION 4 BOOM PLATFORM 4 18 3121619 Figure 4 9 Boom Assembly Sheet 8 of 9...
Page 181: ...SECTION 4 BOOM PLATFORM 3121619 4 19 Figure 4 10 Boom Assembly Sheet 9 of 9...
Page 187: ...SECTION 4 BOOM PLATFORM 3121619 4 25 Figure 4 16 Boom Assembly Torque Values Sheet 1 of 4...
Page 188: ...SECTION 4 BOOM PLATFORM 4 26 3121619 Figure 4 17 Boom Assembly Torque Values Sheet 2 of 4...
Page 189: ...SECTION 4 BOOM PLATFORM 3121619 4 27 Figure 4 18 Boom Assembly Torque Values Sheet 3 of 4...
Page 190: ...SECTION 4 BOOM PLATFORM 4 28 3121619 Figure 4 19 Boom Assembly Torque Values Sheet 4 of 4...
Page 201: ...SECTION 4 BOOM PLATFORM 3121619 4 39 Figure 4 20 Hose Adjustment...
Page 202: ...SECTION 4 BOOM PLATFORM 4 40 3121619 Figure 4 21 Section 3 Boom Cables...
Page 203: ...SECTION 4 BOOM PLATFORM 3121619 4 41 Figure 4 22 Section 4 Boom Cables...
Page 204: ...SECTION 4 BOOM PLATFORM 4 42 3121619 Figure 4 23 Section 5 Boom Cables...
Page 205: ...SECTION 4 BOOM PLATFORM 3121619 4 43 Figure 4 24 Jib Hydraulics Sheet 1 of 7...
Page 234: ...SECTION 4 BOOM PLATFORM 4 72 3121619 Figure 4 44 Powertrack Shimming Instructions...
Page 239: ...SECTION 4 BOOM PLATFORM 3121619 4 77 Figure 4 49 Powertrack Hose Installation Sheet 1 of 4...
Page 240: ...SECTION 4 BOOM PLATFORM 4 78 3121619 Figure 4 50 Powertrack Hose Installation Sheet 2 of 4...
Page 241: ...SECTION 4 BOOM PLATFORM 3121619 4 79 Figure 4 51 Powertrack Hose Installation Sheet 3 of 4...
Page 242: ...SECTION 4 BOOM PLATFORM 4 80 3121619 Figure 4 52 Powertrack Hose Installation Sheet 4 of 4...
Page 252: ...SECTION 4 BOOM PLATFORM 4 90 3121619 NOTES...
Page 432: ...SECTION 5 BASIC HYDRAULIC INFORMATION HYDRAULIC SCHEMATICS 5 180 3121619 NOTES...
Page 527: ...SECTION 6 JLG CONTROL SYSTEM 3121619 6 95 Figure 6 36 LSS Installation Sheet 1 of 4...
Page 528: ...SECTION 6 JLG CONTROL SYSTEM 6 96 3121619 Figure 6 37 LSS Installation Sheet 2 of 4...
Page 529: ...SECTION 6 JLG CONTROL SYSTEM 3121619 6 97 Figure 6 38 LSS Installation Sheet 3 of 4...
Page 530: ...SECTION 6 JLG CONTROL SYSTEM 6 98 3121619 Figure 6 39 LSS Installation Sheet 4 of 4...
Page 710: ...SECTION 7 BASIC ELECTRICAL INFORMATION ELECTRICAL SCHEMATICS 7 118 3121619 NOTES...
Page 711: ......