15. Commissioning instructions
This chapter describes:
•
The dangers that may occur when commissioning instructions and safety precautions are
not observed.
•
How to start up this equipment in a safe way.
•
How to prepare a safe and effective start-up.
This chapter is primarily intended for inspectors and supervisors.
15.1
Safety precautions
Danger!
Risk of injury to personnel and damage to equipment! In addition to the safety precautions in this
document, always read the safety precautions belonging to this equipment before start. Failure
to comply with safety precautions may cause death or injury to personnel. It may also cause dam-
age to or destruction of the equipment.
15.2
Preparations for commissioning
Final check of installation
Before the plant is put into operation, the installation must be checked one last time, see subsec-
tion
7.33 Final installation check.
Personnel requirements
The personnel who is going to start up the plant must be competent and have a thorough knowl-
edge of refrigeration technique. It is moreover necessary that the personnel knows the refrigera-
tion plant and its construction and mode of operation. The instructions in this manual must be
read before start-up.
Johnson Controls Denmark offers courses which deal with operation of and service on the unit in
question. It is recommended that both the supervisor and the operator take these courses.
Training
It must be made sure that all personnel have been trained so that the requirements listed under
Personnel requirements
above are complied with.