11 | Installation Instructions
Figure 3: Example of a Foundation
Cables
Only screened cables should be used. The screen must be connected to the cable glands according to Figure 4: Using
Cable Glands on page 11.
Figure 4: Using Cable Glands
Installing the Linkage Transmission
The Linkage Transmission is delivered with all necessary parts except for the RFU LT TUBE. This part is yard delivery.
The yard should determine the proper length and weld one nut with left threat to one side and one nut with right threat on
the other side.
When the Linkage Transmission is used, the angle of the rods should be exactly 90 degrees at a rudder angle of 0
degrees. The distance d2 from the center of the rudder to the ball and socket joint should be exactly the same as the
distance d1 between center of the rudder feedback axle and the corresponding ball and socket joint, see Figure 5:
Rudder Example with Linkage Transmission (Top View) on page 12.