Table 22: Site Preparation Checklist (continued)
Date
Performed By
For More Information
Item or Task
“Clearance Requirements for Airflow and Hardware
Maintenance on ACX2000 and ACX2100 Routers” on
Plan rack or cabinet location, including
required space clearances.
Secure the rack or cabinet to the floor and
building structure.
Cables
Acquire cables and connectors:
•
Determine the number of cables needed
based on your planned configuration.
•
Review the maximum distance allowed
for each cable. Choose the length of cable
based on the distance between the
hardware components being connected.
Plan the cable routing and management.
RELATED DOCUMENTATION
Installing and Connecting an ACX2000 or ACX2100 Router Overview | 93
ACX2000 and ACX2100 Site Guidelines and
Requirements
IN THIS SECTION
Site Electrical Wiring Guidelines | 70
Clearance Requirements for Airflow and Hardware Maintenance on ACX2000 and ACX2100 Routers | 71
Chassis Physical Specifications for ACX2000 and ACX2100 Routers | 72
69
Summary of Contents for ACX2000
Page 1: ...ACX2000 and ACX2100 Universal Metro Router Hardware Guide Published 2020 09 07 ...
Page 91: ...Front Panel of an ACX2000 Router 47 LEDs on ACX2000 and ACX2100 Routers 57 91 ...
Page 116: ...4 CHAPTER Maintaining Components Maintaining ACX2000 and ACX2100 Components 117 ...
Page 125: ...5 CHAPTER Troubleshooting Hardware Troubleshooting ACX2000 and ACX2100 126 ...
Page 139: ...139 ...
Page 144: ...Restricted Access Warning 144 ...
Page 148: ...148 ...
Page 161: ...Jewelry Removal Warning 161 ...
Page 164: ...Operating Temperature Warning 164 ...
Page 174: ...DC Power Disconnection Warning 174 ...
Page 178: ...DC Power Wiring Sequence Warning 178 ...