Overview of Preparing the Site for the JATP400
To prepare a site for JATP400 appliance installation:
1. Verify that environmental factors such as temperature and humidity do not exceed JATP400
tolerances.
2. Verify that the site and installation plan meets all safety guidelines and requirements.
3. Locate sites for connection of system grounding.
4. Calculate the power consumption and requirements.
5. Plan rack location, including required space clearances.
6. Verify that the plan for power installation meets all electrical safety guidelines.
7. Verify that your rack meets the minimum requirements for the installation of the JATP400 appliance.
8. Plan to secure the rack to the floor and building structure.
9. Plan the cable routing and management.
RELATED DOCUMENTATION
JATP400 Site Guidelines and Requirements | 17
Connecting the JATP400 to Power | 35
JATP400 Installation Overview | 25
JATP400 Site Guidelines and Requirements
IN THIS SECTION
General Site Installation Guidelines for the JATP400 Appliance | 18
JATP400 Appliance Physical Specifications | 18
JATP400 Appliance Rack and Clearance Requirements | 20
Additional Hardware Requirements | 21
17
Summary of Contents for JATP400
Page 1: ...JATP400 Appliance Hardware Guide Published 2021 05 17...
Page 8: ...1 CHAPTER Overview JATP400 System Overview 2 JATP400 Chassis 4...
Page 64: ...The hard drive pops partially out of the slot 57...
Page 65: ...Figure 24 Removing a Drive Carrier g100245 58...
Page 67: ...5 CHAPTER Troubleshooting Hardware Contacting Juniper Networks Technical Assistance Center 61...
Page 69: ...6 CHAPTER Returning the Chassis or Components Returning the JATP400 Chassis or Components 63...
Page 72: ...Maintaining the JATP400 Hard Disk Drive 56 65...