NOTE:
If the router isn’t pulled all the way into the rack by the winch
mechanism, grasp the handles on the shipping covers and carefully slide
the router onto the mounting shelf until the front-mounting flanges contact
the rack rails. You must remove the winch bracket to perform this
procedure.
NOTE:
There must be a minimum of 45-U of usable rack space when
installing the MX2010 into a 45-U rack.
11.
Remove the router transport platform, and set the platform aside.
12.
Remove the winch mount and winch strap plate, and set them aside.
13.
Visually inspect the alignment of the router. To verify that the router is installed properly
in the rack, see that all the mounting screws on one side of the rack are aligned with
the mounting screws on the opposite side and the router is level.
14.
Reassemble the router transport kit, and set aside.
Use the Router Transport Kit to Install the Router In an Open-Frame Rack
NOTE:
Four persons are needed to install the router into a rack.
CAUTION:
Before front mounting the router in a rack, have a qualified
technician verify that the rack is strong enough to support the router's weight
and is adequately supported at the installation site.
To install the MX2010 using a router transport kit:
1.
Using the router transport platform, position the router in front of the rack or cabinet,
centering in front of the rack.
2.
Using a four person team, transport the router to the rack installation location and
center it in front of the rack.
NOTE:
A minimum of 38 in. (96.5 cm) of clearance is required to roll the
chassis sideways.
NOTE:
A minimum of 42 in. (106.7 cm) of circular space is required to
rotate the chassis.
Copyright © 2014, Juniper Networks, Inc.
38
MX2010 3D Universal Edge Router Quick Start