PTX10001-36MR Site Preparation Checklist
summarizes the tasks you need to perform when preparing a site
for a PTX10001-36MR installation.
Table 21: Site Preparation Checklist
Item or Task
For More Information
Performed by
Date
Environment
Verify that environmental factors such as
temperature and humidity do not exceed
router tolerances.
"PTX10001-36MR Environmental
Requirements and Specifications" on
page 49
Power
Measure the distance between external
power sources and the router installation
site.
Calculate the power consumption and
requirements.
•
•
Rack or Cabinet
Verify that your rack or cabinet meets the
minimum requirements for the installation of
the router.
"PTX10001-36MR Rack Requirements"
on page 54
Plan rack or cabinet location, including
required space clearances.
"PTX10001-36MR Clearance
Requirements for Airflow and Hardware
Maintenance" on page 52
Secure the rack or cabinet to the floor and
building structure.