hy-switch for KACO blueplanet hybrid inverters
Page 25
L3 Grid connection
(grid) L3 House
connection (off-grid)
L2 Grid connection
(grid) L2 House
connection (off-grid)
L1 Grid connection
(grid) L1 House
connection (off-grid)
N Grid connection (grid)
N House connection (off-
grid) PE Earth potential
Fig. 9: Grid connection with cable gland and assignment
8.4.
Communication to the inverter
The communication cable requires RJ45 plugs on both sides and must comply with
CAT 5E S/FTP. The length depends on the installation location, but should not exceed
20 m. Cross-over assignments cannot be used.
1.
The hy-switch connection of the blueplanet hybrid inverter must be
connected to the hy-switch connection of the component.