11. Proceed in the same manner to set the cut-out period.
12. Use the «Up» or «Down» keys to select the
Function line.
13. Press «Enter» to switch into setting mode.
14. Use «Up» or «Down» to set the desired
on or Load option.
15. Press the «Enter» key.
The setting is applied.
16. Use the «Up» or «Down» keys to select the
Activate line.
17. Press «Enter».
The check box flashes in the active line.
18. Press the «Up» key.
The check box is activated.
4 0 0 m b a r
0 8 : 1 5 A M
8 0 ° C
Header
5.9 Pulse generator
Menu
Activate
☑
The timer is activated
on :
01h:15m:00s
Cut-in period
off :
01h:15m:00s
Cut-out period
Function
Load
Mode
19. Press «Enter».
The setting is applied.
Result The machine is controlled by the timer.
8.5.3 "Automatic restart" function
The "Automatic restart" function is deactivated after power failure.
If you want to activate the "Automatic restart" function, you can set a delay time for the machine
restart. You ensure so that the electrical system is not overly stressed due to a simultaneous start
of multiple machines.
Setting the automatic restart delay period
If you operate several machines, it is better to start them in sequence.
Use the "Delay time for automatic restart" table to plan the time-delayed machine start. In the
"Start period" column, enter for each individual machine the real time required for the first
possible LOAD. Cumulatively add these values in the "Delay time" column. Enter the value of
the delay time of each machine in the corresponding controller.
The first machine may start immediately and does not require a delay time.
Machine number
Start time [sec]
Delay time [sec]
1
––
––
2
3
4
5
8
Initial Start-up
8.5
Machine start and machine stop
86
Service Manual Controller
SIGMA CONTROL 2 BLOWER ≥ 4.0.X