7.2.2 Special measures for re-commissioning after storage or de-commissioning
➤ Carry out the following before every start-up after long period of storage or de-commissioning:
Storage/de-
commissioning
period longer
than:
Remedy
5 months
➤ Remove the desiccant from the openings in the air intake filters of the en‐
gine and compressor.
➤ Check the air and oil filters.
➤ Drain the preserving oil from the separator tank.
➤ Fill with cooling oil.
➤ Drain the preserving oil from the engine.
➤ Fill up with engine oil.
➤ Check the engine coolant level.
➤ Check the battery charge state.
➤ Reconnect the battery.
➤ Check all fuel lines, engine oil lines and compressor cooling oil lines for
leaks, loose connections, wear and damage.
➤ Clean the bodywork with a grease and dirt dissolving agent.
➤ Check the tyre pressures.
36 months
➤ Have the overall technical condition checked by an authorised
KAESER SERVICE technician.
Tab. 67 Measures for re-commissioning the compressor after a long period of storage or de-commissioning
7.3 Checking installation and operating conditions
➤ Check and confirm all the items in the checklist before starting the machine.
Check
See chapter Confirmed?
➤ Are the operators fully conversant with safety regulations?
–
➤ Have all the positioning conditions been fulfilled?
➤ Is there sufficient cooling oil in the separator tank?
➤ Is there sufficient oil in the engine?
➤ Is the maintenance indicator on the air intake filters (engine and
compressor) OK?
➤ Is there sufficient coolant in the coolant expansion tank?
➤ Is there sufficient fuel in the fuel tank?
–
➤ Is there sufficient tool oil in the tool lubricator? (Option ec)
➤ Is there enough antifreeze in the frost protector? (Option ba)
➤ Are the access doors closed and all body panels in place?
–
➤ Are the tyre pressures OK?
–
Tab. 68 Positioning and operating conditions checklist
7
Initial Start-up
7.3
Checking installation and operating conditions
No.: 9_5898 26 E
Operator manual Portable compressor
M 64
61