Page 10 of 16
2019
/09
/11
2-2. every 3 months (or different, determined by local factors)
• Check axles, hubs and bearings for smooth running, bearing shake, wear or
• Check for bearing play and wear. To check, the swing platform and the univer-
sal joint must be relieved by lifting the platform (e.g. by 2nd person or trestles).
2-2. every 6 months (or different, determined by local factors)
•
Check components for tight fit. Check screw connections and tighten if neces
• Replace lubrication as described in appendix A2 „Replace lubrication at least
• Check playground equipment including all components and construction ele-
ments above and below the playing level for damage caused by wear, vanda-
lism, weather events, rotting, corrosion and element formation, etc. This may
require excavation or access to areas below the playground level and subse-
quent repair of the playground surfacing.
• Check foundations for damage due to wear, vandalism, weather events, rot-
ting, corrosive and element formation, etc. This may require excavation or ac-
cess to areas below the playing level and subsequent repair of the playground
• Inspect the playground surfacing using the inspection procedures and main-
tenance instructions provided by the manufacturer/distributor of playground
floors, particularly with regard to levels of loose fill material.