6
Installation and wiring
6.1
Definition of the connection side
2
1
Front view
Side view
Fig. 2: Water connection position
1
Supply ½“
2
Return ½“
6.2
Requirements governing the installation site
Only install and assemble the unit if the following conditions are met:
Make sure that the ceiling is sufficiently load-bearing to take the weight of the unit (
Make sure that the unit is securely suspended/standing.
Ensure that the airflow can circulate freely.
Provide adequate space for appropriately sized flow and return water connections on site (
There is a power supply on site (
Maximum electrical rating values [
If need be, provide a condensation connection with a sufficient gradient on site.
The load-proof and vibration-free installation of the unit can be guaranteed.