TIP
Assembly, installation and operating instructions
19
6.3.6 Louvres
D
B
A
C
Fig. 7: Louvres
Induction louvre mounting (type 3*101): A + B
Induction louvre mounting, 2-row (type 3*002): A + C + D
6.4
Installation
Actuator with ‘First Open’ function
When delivered, the actuator is normally open in a de-energised state, thanks to the First Open function. This enables
heating mode to run even if the electric wiring is not yet completed.
When subsequently commissioned and with the application of power (for longer than 6 minutes), the First Open function
is automatically unlocked so that the actuator becomes fully operational.
0,5 mm
> 0,5 mm
< 0,5 mm
Power on
> 6 min
Power off
Fig. 8: “First Open” function
Hydraulic connection
Note the following points when connecting the hydraulic side:
Install and test safety components (expansion vessels, pressure relief valves and overflow valves).
Allow adequate space for the air flow (air inlet and outlet).
Summary of Contents for TIP
Page 2: ......
Page 40: ...TIP Assembly installation and operating instructions 40 12 Certificates...
Page 45: ......
Page 46: ......
Page 47: ......