Useful tip: to ensure long-term operation of the generator engine, it is
important to observe the following tips:
- Before connecting the load, allow the engine to run for 1-2 minutes to warm it
up.
- When disconnecting the load after lengthy operation, do not turn off the
generator. Allow the generator to run idle for 1-2 minutes so that it cools down.
!
!
PLEASE NOTE!
ENGINE START
- Do not connect any power consumers to the generator before you start the
engine.
- Turn the ECON switch to the “OFF” position.
- Turn the air choke control knob to the “CLOSE” position.
- Turn the fuel valve handle to the “ON” position (OPEN).
- Set the engine switch to “ON”.
- Pull the manual starter until a slight resistance is felt, then pull it toward you
relatively sharply.
- Slowly turn the manual starter by hand, do not release it abruptly.
- When starting the generator, hold the generator by the carrying handle to
prevent the generator from falling.
- Slowly turn the air choke control knob to the “OPEN” position and then warm
up the engine for 1-2 minutes.
- If the engine does not start, check the oil level.
- Before turning on the connected device, check that the ECON switch is in the
“OFF” position.
Before starting to use the generator, connect the ground wire to the
ground terminal.
Before using the ground terminal, it is necessary to consult a
specialist.
!
!
PLEASE NOTE!
!
!
PLEASE NOTE!
COMMISSIONING
In the first 20 operating hours of the generator, the following requirements
should be met:
1. During commissioning, do not connect power consumers, the power of which
exceeds 50% of the nominal (operating) power of the device.
2. After commissioning, be sure to change the oil. It is better to drain oil while
the engine is still hot after operation to ensure quick and complete oil draining.