24. Crane operation
24. Crane operation
(1610-0030-1E)
This crane is reasonably simple to operate, but even small slips can cause major accidents, so always work steadily one
step at a time.
24-1 Preparations for crane operation
(4210-3246-0E)
24-1-1 Preparations before operating the crane
(T218151-060-0E)
(1)
Move the crane to the firm, level ground. Fully retract the suspension lock cylinders to lock the suspension.
(2)
Set the PTO switch to the "ON" position.
(3) Outrigger setting
1)
Use the outriggers to set the crane in a level position. As a rule,
fully extend all outriggers as far as possible when leveling the
crane and inset the stopper pins in each outrigger to check the
extension width.
2)
Check that all tires are lifted off the ground.
(4) ACS setting
1)
Set the outrigger setting status that corresponds to the outrigger extension width on the working status setting
screen.
2) Set the boom status that corresponds to the boom operation status on the working status setting screen.
3)
Press the ACS display switch to complete the ACS setting.
(5)
Perform the ACS preoperational check procedure.
Be sure to perform the ACS preoperational checks before starting crane operations.
1)
Press the function switch to display the ACS preoperational
check screen. Check that the ACS is working correctly.
Refer to the ACS instruction manual for details of ACS
operation.
2)
After inspection, return the display to the ACS screen.
Summary of Contents for PREMIUM CITYRANGE CR-200RF
Page 2: ...218711 背厚 14 5 mm 中 ...
Page 14: ... 12 4 Dimensions T217591 021 0E Specification of CR 200Rf ...
Page 16: ... 14 MEMO ...
Page 24: ... 22 MEMO ...
Page 30: ... 4 MEMO ...
Page 36: ... 10 MEMO ...
Page 38: ... 12 3 General operation devices 2 Outside the cab ...
Page 60: ... 34 MEMO ...
Page 74: ... 48 MEMO ...
Page 82: ... 56 7 Air conditioner 7 6 Display when errors are detected T217921 020 0E ...
Page 120: ... 94 MEMO ...
Page 129: ... 102 MEMO ...
Page 138: ... 111 17 Drive operation devices Drive operation devices ...
Page 139: ... 112 17 Drive operation devices ...
Page 153: ... 126 17 Drive operation devices ...
Page 154: ... 127 17 Drive operation devices Drive operation devices ...
Page 237: ... 208 21 Crane operation devices 21 Crane operation devices 061A 0005 0E 1 Inside the cab ...
Page 238: ... 209 21 Crane operation devices Crane operation devices ...
Page 239: ... 210 21 Crane operation devices 2 Outside the cab ...
Page 259: ... 230 22 Crane operation when the outriggers are used ON OFF ...
Page 299: ... 270 24 Crane operation NOTE Extension retraction sequence for each boom length ...
Page 320: ...26 Preoperational checks Pre drive checks 290 ...
Page 321: ...Preoperational checks Pre drive checks 26 Preoperational checks Pre drive checks 291 ...
Page 322: ...26 Preoperational checks Pre drive checks 292 ...
Page 329: ...Preoperational checks Pre drive checks 26 Preoperational checks Pre drive checks 299 ...
Page 330: ...26 Preoperational checks Pre drive checks 300 ...
Page 331: ...Preoperational checks Pre drive checks 26 Preoperational checks Pre drive checks 301 ...
Page 332: ... 302 MEMO ...
Page 340: ... 310 MEMO ...
Page 342: ...899 92187110 ...