background image

 

 

KE RT Series UPS 6-10kVA UL 208-220-230-240Vac User Guide English 20180130    This manual is for qualified personnel only 

- 20 -

 

Note 

The BAT+ of the UPS connection poles is connected to the anode of the positive battery, the BAT- is 

connected  to  the  cathode  of  the  positive  battery  and  the  anode  of  the  negative  battery,  the  BAT-  is 

connected to the cathode of the negative battery. 

 

Factory default setting for battery quantity is 16pcs and for battery capacity is 7AH (charger current 

1A). When connecting 18pcs or 20pcs batteries, please re-set the battery quantity and its capacity after 

UPS starts at AC mode. Charger current should be adjusted automatically according to battery capacity 

selected. All related settings can be done through LCD panel or monitoring software. 

 

CAUTION 

Ensure correct polarity battery string series connections. I.e. inter-tier and inter block 

connections are from (+) to (-) terminals. Do not mix new and old batteries, different 

capacities or brands.

     

 

WARNING 

Ensure correct polarity of string end connections to the Battery Circuit Breaker and 

from  the Battery Circuit Breaker to the  UPS terminals.  i.e. (+) to (+) / (-) to (-). 

Disconnect one or more battery cell links in each tier. Do not reconnect these 

links  and  do  not  close  the  battery  circuit  breaker  unless  authorized  by  the 

commissioning engineer.

 

 

4.7

 

UPS Parallel Installation 

The following sections introduce the installation procedures specified to the parallel system. 

 

4.8

 

Cabinet installation 

Connect all the UPS needed to be put into parallel system as below. 

 

 

 

 

Summary of Contents for RT 10KVA

Page 1: ...ES WHETHER SPECIAL DIRECT INDIRECT CONSEQUENTIAL OR INCIDENTAL WHICH MIGHT ARISE OUT OF THE USE OF SUCH INFORMATION THE USE OF ANY SUCH INFORMATION WILL BE ENTIRELY AT THE USER S RISK AND C REMINDS YO...

Page 2: ...the parallel system 21 5 Operation 22 5 1 Operation Modes 22 5 2 Turn on off UPS 22 5 2 1 Connecting with Utility 22 5 2 2 Black Cold start procedure 23 5 2 3 Inverter Off 23 5 2 4 Disconnecting with...

Page 3: ...rent protection in accordance with the National Electrical Code NEC ANSI NFPA 70 Output overcurrent protection and disconnect switch must be provided by others To comply with international standards a...

Page 4: ...r And also support for single phase input Digital Control This series UPS is controlled by Digital Signal Processor DSP which increases reliability performance enables self protection and self diagnos...

Page 5: ...80130 This manual is for qualified personnel only 4 3 UPS Module Overview Front View Rear View Side View 1 handles 2 LCD Display 3 PDU 4 EPO 5 Parallel Port 1 6 Intelligent slot 7 Battery Slot 8 Input...

Page 6: ...nglish 20180130 This manual is for qualified personnel only 5 3 1 LCD control panel LCD control panel introduction 1 INVERTER LED 2 BATTERY LED 3 BYPASS LED 4 ALARM LED 5 LCD display 6 UP button 7 DOW...

Page 7: ...nsible manner Place the cabinet in a protected area that has adequate airflow and is free of humidity flammable gas and corrosion 4 3 Installation notes Place the UPS in a clean stable environment avo...

Page 8: ...equals max load at altitude divided by nominal power of the UPS Altitude m 1500 2000 2500 3000 3500 4000 4500 5000 Load coefficient 100 95 90 85 80 75 70 65 4 4 External Protective Devices For safety...

Page 9: ...rotective earth cable Connect each cabinet to the main ground system For Grounding connection follow the shortest route possible WARNING Failure to follow adequate earthing procedures may result in el...

Page 10: ...a positive and negative double battery framework with 16 optional 18 20 pieces in series A neutral cable is retrieved from the joint between the cathode of the 8th 9th 10th and the anode of the 9th 1...

Page 11: ...ing to battery capacity selected All related settings can be done through LCD panel or monitoring software CAUTION Ensure correct polarity battery string series connections I e inter tier and inter bl...

Page 12: ...a ring configuration between UPS modules as shown below The parallel control board is mounted on each UPS module The ring configuration ensure reliability of the control 4 10 Requirement for the para...

Page 13: ...al AC load This is to avoid paralleling of unsynchronized AC sources This interruption is programmable but typically set to be less than an electrical cycle e g less than 15ms 50Hz or less than 13 33m...

Page 14: ...s later the inverter starts INV and output light up CAUTION Wait for approximately 30 seconds before you press the black start key 5 2 3 Inverter Off When the Utility is normal press ESC OFF button fo...

Page 15: ...Voltage Current 04 Bat Voltage Current 05 Temperature PFC Internal temperature and ambient temperature 06 Load Load 07 Bus voltage Bus voltage 08 Software version DSP version of inverter software 09...

Page 16: ...ternal temperature down 8 Bus voltage 9 Software version 5 4 Parameters setting The setting function is controlled by four buttons ENTER ON ESC OFF UP DOWN ENTER goes into the setting page and value a...

Page 17: ...parallel redundancy quantity setting 5 4 2 Output voltage setting Output voltage setting Note the area marked by the broken line will be flashing Within the mode setting press DOWN or within the frequ...

Page 18: ...nd goes to output voltage setting or battery capacity setting Note When powered by inverter it is necessary to turn off the inverter before setting voltage and frequency level 5 4 4 Battery capacity s...

Page 19: ...quantity setting save the battery quantity setting and goes to battery capacity setting or bypass voltage upper limit setting 5 4 6 Bypass Volt Hi setting Bypass voltage upper limit setting Note the a...

Page 20: ...he bypass voltage lower limit setting and goes to bypass upper limit setting or parallel ID setting 5 4 8 Buzzer Mute Setting Buzzers mute setting Note the area marked by the broken line will be flash...

Page 21: ...est occurs automatically every 30 days There are three kinds of Battery Self test Time as below On1 UPS will transfer to Battery Mode automatically once every 30 days Self test Time is 10 seconds On2...

Page 22: ...D setting save the parallel ID setting and goes to bypass lower limit setting or parallel quantity setting NOTE Parallel cable cannot be connected when setting the parallel parameters 5 4 11 Parallel...

Page 23: ...ing Note the area marked by the broken line will be flashing Within the parallel quantity setting press DOWN to go to the parallel redundancy quantity setting Use button ENTER ON to set the parallel r...

Page 24: ...100 linear load input THDV 1 5 100 non liner load input THDV 1 battery Battery number 16 18 20pcs can be set Battery type VRLA Charge model Boost charge or float charge auto switch Charge time Boost c...

Page 25: ...ty IEC62040 1 UL 1778 CSA C22 2 Max input voltage 320Vac 1Hr EMC IEC 62040 2 FCC Part 15 Class B MTBF 250 000Hr 1 1 400 000Hr MTTR 30min Isolation resistance 2M 500Vdc Isolation intension 2820Vdc 3 5m...

Page 26: ...definition USB communication port 1 2 4 3 Definition of Male port Pin 1 VCC Pin 2 D pin 3 D Pin 4 GND Application use UPSilon2000 Power Management software Available functions of the USB Monitor UPS p...

Page 27: ...LED lit 3 Inverter Thyristor short Beep continuously Fault LED lit 4 Inverter Thyristor broken Beep continuously Fault LED lit 5 Bypass Thyristor short Beep continuously Fault LED lit 6 Bypass Thyris...

Page 28: ...nce per second Fault LED blinking 28 Bypass Site Wiring Fault Once per second Fault LED blinking 29 Output Short circuit Once per second Fault LED blinking 30 Rectifier over current Once per second Fa...