The maintenance period in above table are just the recommended maintenance period, actual
period should be decided by actual installation and use environment. The power station size,
location and environment all may influence the routine maintenance period.
If the PCS is installed in harsh environment with lots of sand and wind, the maintenance
period must be shorted.
6.2 Safety Precautions
To ensure human safety and equipment security, observe the following precautions when maintaining
the equipment.
Please keep in mind that even if the PCS is not running, there still may exist dangerous voltage.
Before maintaining the equipment, wait for about 20 minutes for discharging and use a
multimeter to check the voltage and make sure that the equipment is completely shut down.
Before operating equipment, take off metal articles, such as rings, necklaces, and watches.
Obey safety regulations strictly. For any questions, consult professionals.