(E) Earthing point
The spectrometer body has an M6 earth attachment point below the probe. This can be used
where local codes require it in addition to earthing through the power supply cable.
WARNING
Failure to properly earth the spectrometer may cause serious
injury or death.
Figure 16: ASM0627-10-Z-Cx-Ex-Gx-D3x back and base of the instrument
(F) Purge inlet
The spectrometer purge inlet is used to purge both the spectrometer body and the probe at
the same time through a single connection. The connection is a Legris push-fit fitting. Rigid or
fixed piping may be used if the fitting is compatible and mechanical stress is avoided.
More detail on how to purge the instrument is given in Section 2.2 Purging the IRmadillo.
(G) Communication gland
This is the connection from the spectrometer for remote access, network connection or DCS.
More detail on how to connect using the cables is given in Section 2.3 How to connect data
communications.