Electrical Installation
This shower requires a 230-240 VAC, 47 ~ 63Hz single phase supply. A single 3 Amp switched fused spur should be used
for each Panel. Up to 12 Kelda showers can run from a single 32A 30mA RCBO.
Before connecting to power supply, make sure that the mains terminal is able to sustain 240V and 3A. All electrical instal-
lation to be carried out by an approved electrician in accordance with Part “P” U.K. Building Regulations and to the latest
IEEE standards, or the appropriate regulations in the country of installation.
~~
~~
~~
~~
~~
~~
~~
~~
32A 30mA RCBO
(Up to 12 Showers)
3A Switched Fused Spur
AC 100-240V to DC 24V
Transformer 60W (Sup-
plied)
Kelda Control Hub
1.
Thread the power supply cable through the 16mm cable
gland in the bottom left of the Control Hub.
2.
Connect the cable to the 24V power terminal shown.
(Polarity of connections is not important)
3.
Using a 3mm flat screwdriver, tighten the connections
down and tighten gland nut onto cable
Main Distribution Board
230-240V AC
Electrical Connection
10