BOPHV 020411
2-1
SECTION 2 - INSTALLATION
2.1
UNPACKING AND INSPECTION
This instrument has been thoroughly inspected and tested prior to packing and is ready for
operation. After carefully unpacking, inspect for shipping damage before attempting to operate.
Perform the preliminary operation check as outlined in PAR. 2.5. If any indication of damage is
found, file an immediate claim with the responsible transport service.
2.2
TERMINATIONS
A)
FRONT PANEL: Refer to FIG. 2-2A and Table 2-2.
B)
REAR: Refer to FIG. 2-2B and Table 2-2.
C) INTERNAL CALIBRATION CONTROLS: Refer to FIG. 2-1 and Table 2-1.
FIGURE 2-1. LOCATION OF INTERNAL CALIBRATION CONTROLS
TABLE 2-1. INTERNAL CALIBRATION CONTROLS
REFERENCE DESIGNATION
CONTROL
PURPOSE
ADJUSTMENT PROCEDURE
R18
(±) 10V CAL.
Reference Voltage Calibration
R31
E
O
ZERO
E
O
Pre-amp Zero Adjustment
R36
I
O
ZERO
I
O
Pre-amp Zero Adjustment
R303
I
OX
I
O
Stabilization Compensation