43/44
Scienlab Regenerative AC Emulator
–
Keysight SL1200A Series
–
Operating Instructions
Decommissioning 8
8
Decommissioning
Temporary Decommissioning
1
Switch off system and attached module assemblies, see
2
Clean and maintain system, see
Carrying out Maintenance Work.
After a temporary decommissioning, commissioning must be performed again,
see chapter
Storage Conditions
The ambient conditions as per the
must be observed for
short- and medium-term storage (up to 2 years).
Dismantling, Final Decommissioning
1
Switch off system,
2
Disconnect the power supply to the system and roll up supply cables
and fix them securely on the system.
3
Disconnect all further lines (signal and control lines, load and measur-
ing lines) and roll up the cables.
Disassemble and decommission the system by performing the steps in re-
verse order. All system parts must be disposed of professionally.
NOTICE
Summary of Contents for SL1200A Series
Page 2: ......