Setting Up the Keysight 5500 SPM
5
Keysight 5500 SPM User’s Guide
5-4
Facility Requirements
Following these guidelines for preparing the Keysight 5500 SPM
facility will ensure a smooth installation, will make using the system
more convenient and will improve system performance for the life of
the SPM:
•
Minimize the acoustic noise level from all possible sources, such as
paging speakers, telephone ringer, air conditioner, especially during
data acquisition.
•
Install the equipment as far away as possible from facility equipment
such as air handlers and pumps.
•
Keep far away from any source of strong electromagnetic fields.
•
Reduce the exposure of the SPM to air flow or dramatic temperature
changes. Minimal temperature variation is desirable to minimize
thermal drift during measurements and to minimize settling time..
•
Use dedicated power outlets with surge protection (strongly
recommended).
•
Include a set of organized shelves and drawers for system
components.
•
If gold substrates are frequently used, a hydrogen flame-annealing
station is recommended.
•
Appropriate water sources should be available for temperature
control and biological experiments.