Hardware
Wood Parts
Step 7: Floor Assembly
Part 1
A:
Place 1 (070) Floor Board tight to (040) Slide End Panel and 1 tight to (050) SW Wall Panel then attach each
to the (061) Side Joists with 4 (S20) #8 x 1-3/8” Wood Screws per board. (fig. 7.1 and 7.2)
B:
Place (071) Long Floor Joist tight to the bottom of each (070) Floor Board, centred over the pilot holes on the
(040) Slide End Panel and (050) SW Wall Panel then attach with 2 (S4) #8 x 3” Wood Screws per panel. Attach
(070) Floor Board to (071) Long Floor Joist with 2 (S20) #8 x 1-3/8” Wood Screws per board (fig. 7.1, 7.2 and
7.3)
2 x
Floor Board 1 x 5 x 35-5/8”
1 x
Long Floor Joist 1-1/4 x 3 x 63-1/4”
12 x
#8 x 1-3/8” Wood Screw
4 x
#8 x 3” Wood Screw
070
Fig. 7.2
Fig. 7.1
050
S4
S4
Tight
071
Wall removed
for clarity
x 6 per
board
061
061
Fig. 7.3
Tight
070
S20
S20
071
040
040
S4
050
30
Summary of Contents for Cedar Summit Canyon Ridge
Page 113: ...NOTES 113 ...