12.1 Clearance Requirements
Provide at least 91 cm (36 in.) of clearance in front of the inverter, and a minimum of 15 cm (6
in.) of clearance at the top and bottom of the inverter for ventilation. Ensure the vents remain
unobstructed, and that the Conext XW Pro Power Distribution Panel door has adequate room
to fully open.
12.2 Wall-Mounting
A mounting plate is included with each Conext XW Pro and Power Distribution Panel
(PDP), designed to meet standards for structural and seismic stability. When properly
installed, the system also meets Section 59 of UL 1741 for Static Loads.
Each Conext XW Pro and Power Distribution Panel (PDP) requires a separate generic-
Mounting Plate. Attach the mounting plate to the wall before you attach the Conext XW
Pro or Power Distribution Panel (PDP) to the mounting plate. Each Mounting Plate re-
quires a minimum of four ¼-inch diameter lag bolts or other fasteners (not included).
The fasteners must be strong enough to support 500 lbs (227 kg). The type of fastener
required to secure the mounting plate varies according to the vertical surface and wall
structure of your installation location.
The holes of each Mounting Plate are spaced 16 inches (40 cm) apart, so that the
mounting plate will span two wall studs spaced 16 inches on-center. Additional mounting
holes are provided to allow for other mounting options.