background image

Cetra

®

 

1  

Proper product installation, in accordance with these instructions, is the responsibility of the installing agent. 
If you have any questions concerning these instructions, please call Kimball Office Customer Care. 

2382137 Revision A 

Assembly Instructions 

5.  Tighten screws until the “U” channel is tight against the 

Traxx (figure B). 

 

Note: 

The top edge of the “U” channel should be even with the 

top of the upper Traxx when the panel is the same height of the 
upper Traxx. 

Starter Panel Installation 

Tools Required 

Package Contents 

Tape Measure 
Level 4 ft. or greater 
Philips screwdriver 
Wall fastener 
Fastener tool 

1.  Install the 1/4” X 20 X 1/2” Phillips pan head screws 

through the holes on the inside of the “U” channel (figure 
A) 

 

Note: 

For Panels Less that upper Traxx height use secondary 

fastening (figure A1) 

Note: 

Wall fasteners and hole location are the responsibility of 

the Installer 

Installation 

U channel 
Starter Panel 
1/4” X 20 X 1/2” Phillips pan head screw 
1/4” X 20 weld nuts 

Figure A                                                                   Figure A1 
 

Figure B 

 
 

Dry Wall: 

Must be at least 5/8" thick. Use 3/16" hollow wall 

fasteners or 3/16" toggle bolts with countersunk flat head ma-
chine screws. 

Wood Studs: 

Must be nominal 2" x 4" size, on no more than 

24" center with maximum height of 14 feet restrained at floor 
and ceiling. Use #10x2" countersunk flat head screws. 

Metal Studs: 

Must be "C" channel, 20 gauge, on no more 

than 24" center. Maximum height  of 14 feet restrained at 
floor and ceiling.  Use 3/16" hollow wall fasteners or 3/16" 
toggle bolts with countersunk flat head machine screws. 
Concrete: Use concrete wall anchors with #10x11/2" counter-
sunk flat head machine screws. 

Recommended Fasteners 

2.  Hand turn the 1/2” x 20 weld nuts onto the screws (figure 

A).  Orient weld nut horizontally to allow insertion into 
Traxx.  Do not tighten. 

3.  Position the starter panel “U” channel against Traxx at 

desired location (figure B). 

4.  Level/plumb the “U” channel (figure B). 

Reviews: