Commissioning
Personnel:
n
Unit officer
NOTICE!
Wear suitable protective gloves when using the
unit. These gloves must comply with either PPE
Ordinance 2016/424 or the MDD Directive
93/42/EEC (which will be superseded on 27 May
2021 by MDR Regulation 2017/745).
6.1 Activities during commissioning
WARNING!
Danger of damage and injury due to commis-
sioning by unqualified staff!
If commissioning is performed incorrectly by
unqualified staff, serious damage to the chilled
goods can result, which in turn can seriously harm
patients.
– Have all tasks performed only by staff qualified
for those tasks.
– Keep unauthorised persons away from the
working area.
Commissioning consists of the following activities:
1 - Clean and disinfect the interior of the unit
“Cleaning and disinfection” on page 58
Chapter 7.1 “Switching on the unit”
3 - Program the unit
Chapter 6.2 “Programming the unit”
4 - Wait until the target temperature is reached.
5 - Stock the unit
Chapter 7.5 “Stocking the unit” on page 56
.
6 - Instruct the unit officer
Chapter 6.3 “Instruction and unit