OUTLINE OF SERVICE
MAINTENANCE
4-6
GREASE
4
q
Grease is used to prevent seizure and noises at the joints.
q
This construction equipment is used under heavy-duty conditions. Always use the recommended grease and
follow the change intervals and recommended ambient temperatures given in this Operation and Maintenance
Manual.
q
The nipples not included in the maintenance section are nipples for overhaul, so they do not need grease.
If any part becomes stiff after being used for long time, add grease.
q
Always wipe off all of the old grease that is pushed out when greasing.
Be particularly careful to wipe off the old grease in places where sand or dirt sticking in the grease would
cause wear of the rotating parts.
CARRYING OUT KOWA (Komatsu Oil Wear Analysis)
4
KOWA is a maintenance service that makes it possible to prevent machine failures and downtime. With KOWA,
the oil is periodically sampled and analyzed. This enables early detection of wear of the machine drive parts and
other problems.
We strongly recommend you to use this service. The oil analysis is carried out at actual cost, so the cost is low,
and the results of the analysis are reported together with recommendations which will reduce repair costs and
machine downtime.
KOWA ANALYSIS ITEMS
q
Measurement of density of metal wear particles
This uses an ICP (Inductively Coupled Plasma) analyzer to
measure the density of iron, copper, and other metal wear
particles in the oil.
q
Measurement of quantity of particles
This uses a particle quantifier index measurement machine
to measure the quantity of iron particles of 5
μ
or more,
enabling early detection of failures.
q
Others
Measurements are made of items such as the ratio of water in the oil, density of the antifreeze coolant, ratio of
fuel in the oil, and dynamic viscosity, enabling a highly precise diagnosis of the machine's health.
Summary of Contents for PC450-8
Page 2: ......
Page 3: ...FOREWORD 11 ...
Page 66: ...SAFETY MAINTENANCE INFORMATION SAFETY 2 42 ...
Page 351: ...SPECIFICATIONS 15 ...
Page 355: ...SPECIFICATIONS SPECIFICATIONS 5 5 6 7m Boom PC450 8 ...
Page 356: ...SPECIFICATIONS SPECIFICATIONS 5 6 6 7m Boom PC450LC 8 ...
Page 357: ...SPECIFICATIONS SPECIFICATIONS 5 7 6 7m Boom PC450LCHD 8 ...
Page 359: ...SPECIFICATIONS SPECIFICATIONS 5 9 7 0m Boom PC450 8 ...
Page 360: ...SPECIFICATIONS SPECIFICATIONS 5 10 7 0m Boom PC450LC 8 ...
Page 410: ...SUPER LONG FRONT BOOM AND ARM ATTACHMENTS ANDD OPTIONS 6 50 ...
Page 436: ...OPERATION HIGH REACH DEMOLITION EQUIPMENT 27M 7 26 3 Extend arm cylinder Arm cylinder ...
Page 469: ...INDEX 18 ...
Page 470: ...INDEX 8 2 ...
Page 473: ...COLOPHON 18 ...