5.
Mount a shackle to boom pins and the counter weight. Hang
the wire rope.
6.
The length off the wire rope and the lifting angle must be as
shown in the figure on the right.
7.
When lifting, make sure that there is no change in the position
due to possible leakage in the hydraulic circuit on the boom
cylinder head side.
8.
When the machine leaves the ground, stop the machine and
make sure sufficiently that the machine is balanced.
Then, lift the machine slowly.
Summary of Contents for PW160-7H
Page 2: ......
Page 3: ...PW160 7H VEAM390100 3 FOREWORD ...
Page 12: ...LOCATIONS OF PLATES TABLE TO ENTER SERIAL NO AND DISTRIBUTOR FOREWORD 12 PW160 7H VEAM390100 ...
Page 18: ...18 PW160 7H VEAM390100 ...
Page 220: ...TROUBLESHOOTING OPERATION 220 PW160 7H VEAM390100 ...
Page 305: ...PW160 7H VEAM390100 305 SPECIFICATIONS ...
Page 307: ...SPECIFICATIONS SPECIFICATIONS PW160 7H VEAM390100 307 1 PIECE BOOM ...
Page 308: ...SPECIFICATIONS SPECIFICATIONS 308 PW160 7H VEAM390100 2 PIECE BOOM ...
Page 345: ......