Transportation
OPERATION
Lifting machine
3-100
Lifting machine
0.
WARNING
When lifting the machine, if the wire rope is not fitted correctly the machine may fall and cause seri-
ous injury or even death. Raise the machine 100 to 200 mm (3.9 to 7.9 in) from the ground, check that
the machine is horizontal and that there is no slack in the wire rope, then continue to lift the machine.
Before lifting the machine, always stop the engine and lock the brakes. Lock front frame and rear
frame with safety bar.
Lifting operations using a crane must be carried out by a qualified operator.
Never raise the machine with any worker on it.
Always make sure that the wire rope used for lifting the machine is of ample strength for the weight of
the machine.
Never try to lift the machine at any position or in any posture other than the posture specified.
Never go under the machine when it is raised.
CAUTION
When the machine is raised, check that there is no oil leakage from the hydraulic circuits.
When carrying out the lifting operation, please contact your Komatsu distributor.
NOTICE
The lifting procedure applies to machines with standard specifications.
The method of lifting differs according to the attachments and options actually installed. In such cases,
please contact your Komatsu distributor for information.
For details of the weight, see “Weight table on page 3-101“.
Summary of Contents for WA250PT-5H
Page 2: ......
Page 3: ...FOREWORD 11...
Page 16: ...Contents FOREWORD 1 14...
Page 24: ...SAFETY 2 2...
Page 58: ...Precautions with tires SAFETY Precautions when storing tires 2 36...
Page 60: ...OPERATION 3 2...
Page 233: ...TECHNICAL DATA 45...
Page 235: ...TECHNICAL DATA Technical data 5 3...
Page 250: ...Central lubrication system ATTACHMENTS OPTIONS 6 14...
Page 251: ...INDEX 67...
Page 252: ...INDEX 7 2...
Page 255: ...Index 7 5...