Fully assembled RHP PRO 10-70 size units can be lifted by crane only if there are no additional sections connected (for
example: heaters, coolers, silencers). Units of other sizes or units with connected additional sections can be lifted only when
it‘s fixed to reinforced mounting frame (ordered separately).
L
>L
Max. 60°
RHP 10-70
RHP 10-70
RHP 80-90
Max. 4 m
RHP 10-40
Fig. 14.
Lifting AHU fully assembled
1
•
Air handling units are heavy, therefore care must be taken during lifting, carrying or moving
operations. Use personal protection equipment, do not stand under a suspended unit or a part
thereof.
•
Only an employee qualified to operate a forklift truck or crane and familiar with the principles of
cargo lifting and safety requirements, must perform unloading or lifting operations.
•
It must be ensured that the casing is not crushed or otherwise damaged by straps or ropes dur-
ing lifting operations. Use of special supporting structures (traverses) is recommended.
•
When lifting the unit or section thereof, note that their center of gravity may differ from the geo-
metric center of the load.
•
Mounting of separate air handling units in stacks is not allowed unless it’s construction design is
intended for such installation.
•
Before installation AHU must be stored in clean and dry premises in their original packaging. If
the unit is installed but not yet in use, all connection openings must be tightly closed and the
unit must be additionally protected against environmental influences (dust, rain, cold, etc.).
1
Lifting means (pipes, belts, ropes, traverses) are not included.