LOG INSTALLATION
INITIAL BURN PERIOD
Due to the make up of the logs/ refractory brick panels, the
curing process may take up to 4 hours of burn time. During
this period, the log & refractory will discolor but will return to
their true color once curing is complete. Do not burn this fire-
place without the glass properly in place.
***Make sure appliance owner is aware of this***
Page 19
G)
#932 DV LOG INSTALLATION. See Figures 13A - 13C
This #932-500A log set includes: (1) „AD‟ log (1) „BI‟ log
(1) „AJ‟ log
(1) „AG‟ log (2) „M‟ logs (1) „C‟ log
(1) „HB‟ log (1) Rock wood embers pkt.
NOTE: THE „AD‟, „AG‟, & „HB‟ LOGS HAVE ALIGNMENT HOLES INCORPORATED INTO THE BOTTOM AND SHOULD BE
PLACED ONTO THE CORRESPONDING PINS IN THE BURNER COVER. THE „BI‟ LOG IS NOTCHED AND SHOULD BE
POSITIONED ONTO THE BURNER COVER PLACING THE NOTCHED OUT SECTIONS IN THE LOG TO THE BRACKETS
IN THE CENTER OF THE BURNER COVER.
1. Place the „BI‟ log onto the center of the burner cover align-
ing the notches in the bottom of the log to the brackets in
the burner cover. Figure 13A.
2.
Place the „AD‟, „AG‟, „HB‟ & „AJ‟ logs into position on the
burner cover aligning the holes in the bottom of the logs to
the corresponding pins in the burner cover. Figure 13B.
IMPORTANT: DO NOT ALLOW ANY PORTION OF THE LOGS TO
COVER THE BURNER PORTS.
3. Place rock wool embers as desired onto the base logs &
burner to enhance flame & glowing effect
.
4. Position top logs „M‟ and „C‟ onto the previously positioned
logs as shown in Figure 13C.
5. Place additional rock wool ember material as desired onto
the logs to enhance glowing effect.
NOTE: You will not use all the rock wool ember material at this
time. Do not plug burner portholes or use excessively.
Figure 13A
Figure 13C
Figure 13B
BI
M
M
BI
AG
HB
AD
C
AJ