3. INSTALLATION AND SETUP
©2014 Kraus Global Ltd.
14
Retail CNG Dispenser Manual
3.2 Pre-installation
CAUTION
Kraus CNG dispensers must be situated in such a way that there are no
obstructions, such as a wall or gate, that may entangle the dispenser
hose. This is to ensure proper functioning of the hose assembly’s
breakaway coupling.
3.2.1 Site preparation
Please observe the following guidelines prior to constructing
dispenser pits:
Be sure to allow room inside the
dispenser pit to properly tie-in the gas
lines to the inline filters and manual
isolation valves.
Make provisions for tubing and electrical
conduits prior to pouring the concrete
pad.
Filters must be installed upstream of the
dispenser.
Due to potential weld slag, filings, rust,
dirt, and water, dispensing lines should be
purged to the atmosphere at the
dispenser. This can be done by blowing
nitrogen through the lines.
All dispensing lines must be purged,
pressurized, and leak tested. Afterwards,
manual isolating valves in the dispenser
pit must also be leak tested. The
dispenser must only be connected to the
lines after these have been accomplished.
ATTENTION
Please refer to your
Construction drawings
for dispenser dimensions.