ASSEMBLY INSTRUCTIONS
8. Fit the relays back into position.
A
Secure all the relays that will face upwards.
9. Remove the foot mat and cut the upper layer made of
sponge of the floor mat as shown in the following
figure.
10. Pass the wire harness through the foot mat as shown
in the following figure and connect the 3rd function
control harness and the ON/OFF switch harness.
And then pass the solenoid valve harness through the
hole of the floor.
11. Connect the wire harness and solenoid valve harness.
And then, bind them by the cord band as shown below.
(1) Relay
(2) Wire harness
(1) Foot mat
(2) Layer of sponge
(A) Cut
(1) Wire harness
(2) 3rd function control harness
(3) ON/OFF switch harness
(4) Solenoid valve harness
(1) Solenoid valve harness 1
(2) Solenoid valve harness 2
(3) Band