7
Roller Shaft
Bolts of Bracket Fixing Bar
Step 4: Roller Chain Installation
A) Prepare proper length of Roller Chain accordance with pipe diameter.
20” – 24” (500mm – 600mm)
1.5 m (Length: 60 in.)
B) Use a chain joint to connect the Roller Chain to the Machine Body or additional Roller Chain.
(Pict.5)
Pict.5
Step 5: Main Body Placement and Guiding Device Adjustment
A) Place the Main Body on the pipe. Make sure the Guide Rollers are placed on the Guide Ring.
After placing the Main Body on the pipe, check if the two Drive Shaft Pulleys (V-Belt) and the
two Wheels are on the pipe. (Refer to Fig.1)
B) Loosen the two bolts of the Bracket Fixing Bar. (Fig.5) Adjust the Roller Shafts to the center of
the pipe. Tighten the two bolts of the Bracket Fixing Bar firmly. (Pict.6)
Fig.5
Pict.6