(2) Detaching and refitting the transfer belt
Follow the procedure below to replace the transfer belt.
Caution:
When handling the transfer belt, hold the both end of the transfer belt (within 10 mm), never touch the surface with bare
hand.
Be careful not so as to adhere grease on the surface of the transfer belt.
Procedure
1. Remove the transfer unit (see page 1-5-49).
2. Rotate the transfer front guide and fit the
angle of the end of the inserted shaft as
shown in the figure, and then remove the
transfer front guide from the transfer unit.
3. Remove the spring from the transfer unit.
Figure 1-5-105
4. Remove each screw at front and rear trans-
fer unit, and rotate the transfer belt roller as
shown in the figure.
Figure 1-5-106
Front transfer guide
Transfer unit
Inserted shaft
Spring
Transfer belt roller
Summary of Contents for TASKalfa 620
Page 1: ...SERVICE MANUAL Published in August 2009 842KP112 2KPSM062 Rev 2 TASKalfa 620 820 ...
Page 4: ...This page is intentionally left blank ...
Page 10: ...This page is intentionally left blank ...
Page 144: ...2KN 2KP 1 3 106 This page is intentionally left blank ...
Page 308: ...2KN 2KP 1 5 88 This page is intentionally left blank ...
Page 412: ...2KN 2KP 2 3 60 This page is intentionally left blank ...
Page 435: ...1 1 INSTALLATION GUIDE INSTALLATION GUIDE FOR SIDE FEEDER ...
Page 442: ...INSTALLATION GUIDE FOR LARGE SIZE SIDE FEEDER ...
Page 460: ...INSTALLATION GUIDE FOR DOCUMENT FINISHER ...
Page 475: ...INSTALLATION GUIDE FOR CENTERFOLD UNIT ...
Page 490: ...INSTALLATION GUIDE FOR MULTI JOB TRAY ...
Page 501: ...INSTALLATION GUIDE FOR PUNCH UNIT ...
Page 512: ...INSTALLATION GUIDE FOR STOPPER GUIDE ...
Page 515: ...INSTALLATION GUIDE FOR PRINTING SYSTEM ...
Page 518: ...INSTALLATION GUIDE FOR SCAN SYSTEM ...
Page 520: ......
Page 521: ......