![background image](http://html1.mh-extra.com/html/kyocera/taskalfa-620/taskalfa-620_service-manual_2015981468.webp)
8
24
24
C
23
B
I
J
21.
メイントレイ (B) にナット (I)2 個をはめ込む。
22.
メイントレイ (B) をピン (J)2 個で取り付ける。
23.
サブトレイ (C) をフィニッシャ(A) 本体の穴 (23) に上からはめ込んで取り付ける。
24.
ルミラ (24)2 枚を取り外す。
21.
Insert the two nuts (I) into the main tray (B).
22.
Secure the main tray (B) with two pins (J).
23.
Install the sub tray (C) by fitting it from above into the hole (23) on the finisher (A) unit.
24.
Remove the two Lumiror films (24).
21.
Insérer les deux écrous (I) dans le plateau principal (B).
22.
Fixer le plateau principal (B) avec deux boulons (J).
23.
Installer le sous-plateau (C) en le fixant par dessous dans l’orifice (23) situé sur le retoucheur (A).
24.
Déposer les deux films Lumiror (24).
21.
Inserte las dos tuercas (I) en la bandeja principal (B).
22.
Asegure la bandeja principal (B) usando dos pernos (J).
23.
Instale la bandeja secundaria (C) ajustándola desde arriba en el hueco (23) de la unidad del
finalizador (A).
24.
Quite las dos películas Lumiror (24).
21.
Setzen Sie die beiden Muttern (I) in das Hauptfach (B) ein.
22.
Sichern Sie das Hauptfach (B) mit zwei Stiften (J).
23.
Installieren Sie das Unterfach (C), indem Sie es von oben in die Aussparung (23) des Finishers
(A) einsetzen.
24.
Entfernen Sie die beiden Luminor-Folien
(24).
21.
Inserire i due dadi (I) nel vassoio principale (B).
22.
Fissare il vassoio principale (B) con due piedini (J).
23.
Installare il vassoio secondario (C) fissandolo da sopra nel foro (23) sull’unità finitrice (A).
24.
Rimuovere i due film Lumiror (24).
Summary of Contents for TASKalfa 620
Page 1: ...SERVICE MANUAL Published in August 2009 842KP112 2KPSM062 Rev 2 TASKalfa 620 820 ...
Page 4: ...This page is intentionally left blank ...
Page 10: ...This page is intentionally left blank ...
Page 144: ...2KN 2KP 1 3 106 This page is intentionally left blank ...
Page 308: ...2KN 2KP 1 5 88 This page is intentionally left blank ...
Page 412: ...2KN 2KP 2 3 60 This page is intentionally left blank ...
Page 435: ...1 1 INSTALLATION GUIDE INSTALLATION GUIDE FOR SIDE FEEDER ...
Page 442: ...INSTALLATION GUIDE FOR LARGE SIZE SIDE FEEDER ...
Page 460: ...INSTALLATION GUIDE FOR DOCUMENT FINISHER ...
Page 475: ...INSTALLATION GUIDE FOR CENTERFOLD UNIT ...
Page 490: ...INSTALLATION GUIDE FOR MULTI JOB TRAY ...
Page 501: ...INSTALLATION GUIDE FOR PUNCH UNIT ...
Page 512: ...INSTALLATION GUIDE FOR STOPPER GUIDE ...
Page 515: ...INSTALLATION GUIDE FOR PRINTING SYSTEM ...
Page 518: ...INSTALLATION GUIDE FOR SCAN SYSTEM ...
Page 520: ......
Page 521: ......