Canopy One (1) and Two (2) Light Rows
Refrigeration Piping and Dehydration
Opening a Ferrule Hole
The refrigeration lines are located under the deck pans. A refrigeration outlet is provided in all four
corners. All refrigeration lines need to be as close to the drain pan as possible so as not to obstruct the air
pattern or block the deck pans. After refrigeration lines have been connected and pressure tested, fill case
pipe penetration with spray foam. Let spray foam dry, cut excess foam flush with inside of case bottom
and then add a layer of silicone sealant for a water tight seal.