With 2 people working simultaneously on each side of the array,
connect the
front
rigging points between KARA-DOWNK1 and K1
as follows:
a.
Remove the front bottom R-BLP from the bottom K1.
b.
Rotate the KARA-DOWNK1 upwards so as to align the front
rigging point with the K1.
c.
Connect the front rigging point by re-inserting the front bottom
R-BLP on the K1.
Figure 48: Front rigging point connection between KARA-
DOWNK1 and K1
8.
With 2 people working simultaneously on each side of ARRAY#1, connect the rear rigging points between
KARA#1 and KARA#2 & 3 as follows:
a.
Grab the back handle of KARA#2 and rotate KARA#2 & 3 upwards so as to align the rear rigging point
between KARA#2 and KARA#1.
b.
Attach the rear bottom
link
R-BLP on KARA#1.
c.
Raise the array and remove the flight-case tray from the rigging location.
Figure 49: Rear rigging point connection between KARA#2 and KARA#1
a.
b.
c.
c.
a.
b.
Summary of Contents for K1
Page 2: ...w w w l a c o u s t i c s c o m ...
Page 68: ...w w w l a c o u s t i c s c o m ...
Page 69: ...w w w l a c o u s t i c s c o m ...
Page 70: ...w w w l a c o u s t i c s c o m ...