Rigging procedures
K2 enclosures on K1-SB
Procedure
References
1.
Stack as many K1-SB enclosures as necessary.
K1 rigging manual
2.
Position and attach a K2-BUMP on the K1-SB stack.
L - Attaching K1 or K1-SB under K2-BUMP
(p.113)
3.
Position and attach an upside down K2 on the K2-BUMP and add as
many K2 enclosures on top of the rst one.
C - Attaching K2-JACK stabilizers to K2-
(p.75)